Questions # 21:

As the Sprint planning progresses, the workload has grown beyond the development team's capacity. Which action makes most sense for the Team?

Options:

A.

Work overtime for the Sprint


B.

Collaborate with the Product Owner and potentially remove or change items


C.

Cancel the Sprint


D.

Star the Sprint and recruit additional team members


Expert Solution
Questions # 22:

A line in the Agile Manifesto reads, "____________ and _____________ over processes and tools". Please select which option best completes the statement.

Options:

A.

Customer; Individuals


B.

People; Relationships


C.

Customers; Employees


D.

Individuals; Interactions


Expert Solution
Questions # 23:

Which of the following are activities found in the Scrum framework?

Options:

A.

Scrum planning


B.

Daily standup


C.

Scrum review


D.

Daily planning


Expert Solution
Questions # 24:

Which of the following statements best describes Product Backlog items?

Options:

A.

Undefined or poorly defined Product Backlog items should be placed on the Product Backlog with a low priority


B.

All Product Backlog items are the result of a(n) analysis, requirements and/or design phase(s).


C.

Undefined or poorly defined Product Backlog items should be kept out from the Product Backlog until sufficient detail is known.


D.

Every Product Backlog item, whether low priority or high priority, should possess sufficient detail for the Team to complete in a Sprint.


Expert Solution
Questions # 25:

What is the Scrum?

Options:

A.

A framework within which people can address complex adaptive problems, while productively and creatively delivering products of the highest possible value


B.

It's not a Agile Framework


C.

Scrum is a complete process to develop software


D.

None of above


Expert Solution
Questions # 26:

Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?

Options:

A.

The development team cannot meet their Sprint commitment to complete work if requirements are changing


B.

A Sprint cycle is not enough time for senior management review and approve changes


C.

This forces Product Owners to focus on what is really important for the team to develop.


D.

The development team must be able to limit the Product Owner authority


Expert Solution
Questions # 27:

The most encouraged time of day to hold a Scrum Daily Meeting is:

Options:

A.

A beginning of the day


B.

Immediately after lunch


C.

4:30 PM


D.

7:00 PM


Expert Solution
Questions # 28:

Select which of the following statements is the most accurate.

Options:

A.

The Scrum Master is responsible for documenting the Sprint Retrospective discussion.


B.

The Scrum Master is responsible for summarizing the Sprint Retrospective discussion

and reporting the discussions to Senior Management.


C.

The Product Owner is responsible for summarizing the Sprint Retrospective discussion

and reporting the discussions to Senior Management.


D.

The Scrum Master is responsible for facilitating and participating in the Sprint

Retrospective


Expert Solution
Questions # 29:

___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.

Options:

A.

Scrum Master


B.

Scrum Owner


C.

Product Owner


D.

Stakeholder


Expert Solution
Questions # 30:

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Options:

A.

The development team should negotiate with the Product Owner on the definition of "done".


B.

The development team should work the extra 8 hours to complete their commitment to the Product Owner


C.

The development team should place the two Product Backlog items back onto the Product Backlog


D.

The development team should keep the three tasks on the Sprint Backlog for the next Sprint and complete those tasks first


Expert Solution