Question #: 1
Topic #: 1

You are configuring the Job Change business process. You need to determine whether to send a step to the current manager or the proposed manager.

What option can you use?


A.

Maintain Advanced Routing Restriction


B.

Validation Condition rule


C.

Routing Modifier


D.

Entry Condition rule


Get Premium Workday-Pro-HCM-Core Questions