SDLCSA Exam Topic 1 Question 7 Discussion:
Question #: 7
Topic #: 1

What are the full steps and proper order for replacing a failed power supply unit in the SYS-421GE-TNHR2-LCC system?


A.

Lift the yellow lock to unlock the release lever > Lift the release lever and use it to pull out the failed power supply unit > Replace the failed power supply unit with a new one


B.

Lift the red lock to unlock the release lever > Lift the release lever and use it to pull out the failed power supply unit > Replace the failed power supply unit with a new one > Ensure the gold connector pins are on the top > Push the new power supply unit into the tray > Push the release lever down and in until it clicks > Ensure the red lock on the release lever is locked


C.

Lift the blue lock to unlock the release lever > Push the release lever down and in until it clicks > Ensure the red lock on the release lever is locked


D.

Lift the release lever and use it to pull out the failed power supply unit > Replace the failed power supply unit with a new one > Push the new power supply unit into the tray > Push the release lever down and in until it clicks


Get Premium SDLCSA Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.