In this planning process, a response or strategy is developed for each item in the prioritized risk listing. It may include a primary choice and a backup option.
Responses to risk can be categorized in one of three ways:
Accepting the consequences if the event occurs
Active acceptance would involve developing a contingency plan that would be executed if the risk occurs
Passive acceptance would allow the risk event to occur (e.g., making less money if the project is a few weeks late)
Avoiding the consequences by eliminating possibility of the event occurring
Mitigating the risk (reducing it's expected value) by:
Minimizing the probability of occurrence
Minimizing the value of the impact
Deflecting (or transferring) the risk elsewhere (in a software project this might mean passing the risk onto a subcontractor or to the customer).
Options Selected by Other Users:
Option A: (20 votes)
100%
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit