ServiceNow Certified Implementation Specialist - Strategic Portfolio Management CIS-SPM Question # 17 Topic 2 Discussion

ServiceNow Certified Implementation Specialist - Strategic Portfolio Management CIS-SPM Question # 17 Topic 2 Discussion

CIS-SPM Exam Topic 2 Question 17 Discussion:
Question #: 17
Topic #: 2

Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?


A.

'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'.


B.

'Enable altering of planned date for task in WIP/Closed'.


C.

'Rollup project start date from tasks'.


D.

'Calculate ROI percentage based on a project's estimated cost and its net value'.