SMC Exam Topic 4 Question 34 Discussion:
Question #: 34
Topic #: 4

Which of the following is true about a Prioritized Product Backlog?


A.

A Prioritized Product Backlog should not have the most valuable User Story on top, because it could be

risky.


B.

Greater value items, although potentially riskier, are given higher priority in a Prioritized Product Backlog.


C.

Uncertainty should be ruled out of the Risk-adjusted Prioritized Product Backlog.


D.

For a Sprint to succeed, User Stories picked for a Sprint should be interlinked with those selected for

subsequent Sprints.