Scrum SAFe Product Owner/Product Manager POPM (6.0) SAFe-POPM Question # 12 Topic 2 Discussion

Scrum SAFe Product Owner/Product Manager POPM (6.0) SAFe-POPM Question # 12 Topic 2 Discussion

SAFe-POPM Exam Topic 2 Question 12 Discussion:
Question #: 12
Topic #: 2

What is one strategy for managing complex critical path challenges?


A.

Adjust work between teams or split Features and Stories


B.

Distribute work to other teams


C.

Sequence work to eliminate same Iteration dependencies


D.

Allocate work between teams based on forecasted capacity


Get Premium SAFe-POPM Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.