What activities would a Product Owner typically undertake in the phase between the end of the
current Sprint and the next Sprint's Sprint Planning?
(choose the best answer)
Working with the Quality Assurance departments on the Increment of the current
Sprint.
There are no such activities. The next Sprint starts immediately after the current
Updating the project plan with the stakeholders.
Refining the Product Backlog.