The Developers have struggled to get all of their forecasted work done during the last three

Sprints. As a Product Owner what steps could you take to help the Developers improve their

ability to deliver a done Increment?

(choose the best two answers)


A.

Ask the Scrum Master to help the Developers learn techniques for improving

their ability to forecast work.


B.

The Product Owner can spend more time with the Developers.


C.

Ensure that all Developers are top performers.


D.

Add more people to the team so they can get more done.