Question #: 16
Topic #: 2

A Scrum Team consists of Developers working from globally distributed locations. Organizing the Scrum events requires conferencing tools that are not easily available within the organization. The Developers propose doing a Daily Scrum only on Tuesdays. Which are the most appropriate responses for their Scrum Master?

(choose the best two answers)


A.

Help the Developers understand that lowering the frequency of communication will only increase the feeling of disconnect between the team members.


B.

Coach the Developers on why a daily frequency is important as an opportunity to update the Sprint Plan and how it helps the team organize work toward achieving the Sprint Goal.


C.

Acknowledge and support this self-managing team's decision


D.

Have the Developers vote to make sure there is consensus within the team