Scrum Professional Scrum Master II PSM-II Question # 14 Topic 2 Discussion

Scrum Professional Scrum Master II PSM-II Question # 14 Topic 2 Discussion

PSM-II Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

A Scrum Team selected a Product Backlog item during Sprint Planning. However, at the end of the Sprint the work does not meet the Definition of Done. What two things should happen with this incomplete Product Backlog item?

(choose the best two answers)


A.

Review the item, add the done part of the estimate to the velocity and create a Story for the remaining work.


B.

The item is not included in the Increment for this Sprint.


C.

Only the stakeholders decide over acceptance of undone work and whether to

release it.


D.

It is put on the Product Backlog for the Product Owner to decide what to do with it.