Scrum Professional Scrum Master I PSM-I Question # 70 Topic 8 Discussion

Scrum Professional Scrum Master I PSM-I Question # 70 Topic 8 Discussion

PSM-I Exam Topic 8 Question 70 Discussion:
Question #: 70
Topic #: 8

What are two effective ways for the Scrum Team to make non-functional requirements visible?

(choose the best two answers)


A.

Run the integration and regression tests before the end of the Sprint, and

capture the open work for the Sprint Backlog of the next Sprint.


B.

Put them on a separate list on the Scrum board, available for all to see.


C.

Add them to the Definition of Done so the work is taken care of every Sprint.


D.

Add them to the Product Backlog to ensure transparency.