The answer is A. True. The Sprint Backlog is a result of Sprint Planning, and it includes the Sprint Goal. According to the Scrum Guide, the Sprint Backlog is composed of the Sprint Goal (why), the set of Product Backlog items selected for the Sprint (what), as well as an actionable plan for delivering the Increment (how) 1 . The Sprint Goal is the single objective for the Sprint, and it provides coherence and focus for the Scrum Team 2 . The Sprint Backlog is a plan by and for the Developers, and it is updated throughout the Sprint as more is learned 2 .