According to the Scrum Guide, the Product Owner does not make sure that the Developers select enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Developers are responsible for selecting how much work they can do in a Sprint, based on their capacity and past performance. The Product Owner may influence them by ordering and clarifying the Product Backlog items, but does not control their selection.