The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?


A.

Add the item to the current Sprint and drop an item of equal size.


B.

Add the item to the current Sprint without any adjustments.


C.

Inform the Product Owner so he/she can work with the CEO.


D.

Add the item to the next Sprint.