According to the Scrum Guide, multiple Scrum Teams working on the same product do not have to have the same Sprint start date. They may start their Sprints at different times, as long as they synchronize their work and integrate their Increments at least by the end of each Sprint. The other option is not valid, as it implies that having the same Sprint start date is mandatory for multiple Scrum Teams.