Scrum Professional Scrum Master I PSM-I Question # 31 Topic 4 Discussion

Scrum Professional Scrum Master I PSM-I Question # 31 Topic 4 Discussion

PSM-I Exam Topic 4 Question 31 Discussion:
Question #: 31
Topic #: 4

What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity? (Choose two.)


A.

By ensuring the meetings start and end at the proper time.


B.

By removing impediments that hinder the Development Team.


C.

By facilitating Development Team decisions.


D.

By keeping high value features high in the Product Backlog.