The correct answers are D and E, because these are two activities that a Product Owner can engage in during a Sprint. The Scrum Guide states that “the Product Owner is responsible for maximizing the value of the product resulting from work of the Development Team.” Therefore, the Product Owner can answer questions from the Development Team about items in the current Sprint, and work with the stakeholders to understand their needs and expectations.