TheProduct Ownerhas the final authority toorder the Product Backlogto maximize value. They are responsible for ensuring that the most valuable and important work is prioritized so that the Scrum Team delivers maximum value in each Sprint.
According to the2020 Scrum Guide:
The Product Owner is accountable formanaging the Product Backlog, which includes ordering items to best achieve the Product Goal.
While the Developers may provide input, the final decision on ordering lies with the Product Owner.
Why the other options are incorrect:
A. Lead Developer:Scrum does not have a "Lead Developer" role or accountability.
B. Scrum Master:The Scrum Master facilitates and coaches but does not manage or order the Product Backlog.
D. Developers:While Developers provide input during refinement and Sprint Planning, they do not have the authority to order the Product Backlog.
Chosen Answer: