The Coach Sync (sometimes referred to as the Scrum of Scrums or SM/TC Sync) is a coordination event within SAFe® where Scrum Masters and Team Coaches from the Agile Release Train (ART) meet to discuss progress, dependencies, and impediments that affect multiple teams.
This event provides a forum for escalating and addressing ART-level impediments that cannot be resolved within a single team. The RTE (Release Train Engineer) typically facilitates this meeting to ensure transparency and problem-solving across teams.
From SAFe guidance:
“The Coach Sync allows Scrum Masters and Team Coaches to discuss cross-team progress and impediments, escalating those that require ART-level visibility or resolution.”
Therefore, the correct answer is C. Coach Sync. This event enables effective synchronization among teams and promotes continuous improvement across the ART.