SP-SAFe-Practitioner Exam Topic 7 Question 69 Discussion:
Question #: 69
Topic #: 7

The Scrum Master/Team Coach wants to establish a team's initial capacity. The team has two testers, three developers, one full-time Scrum Master/Team Coach, and a Product Owner split between two teams. What is their capacity before calculating for time off?


A.

48


B.

32


C.

52


D.

40