Scaled Agile SAFe for Teams SP (6.0) - SAFe Practitioner SP-SAFe-Practitioner Question # 48 Topic 5 Discussion

Scaled Agile SAFe for Teams SP (6.0) - SAFe Practitioner SP-SAFe-Practitioner Question # 48 Topic 5 Discussion

SP-SAFe-Practitioner Exam Topic 5 Question 48 Discussion:
Question #: 48
Topic #: 5

On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?


A.

Defer acceptance testing to the next Iteration


B.

Communicate the status of the Iteration to all stakeholders


C.

Have an emergency Iteration Planning meeting


D.

Stop the current Iteration and plan a new Iteration with the new knowledge


Get Premium SP-SAFe-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.