The Scrum Master/Team Coach wants to establish a team's initial capacity. The team has two testers, three developers, one full-time Scrum Master/Team Coach, and a Product Owner split between two teams. What is their capacity before calculating for time off?


A.

32


B.

52


C.

40


D.

48