At the end of Day 1 of PI Planning, managers and key stakeholders meet to review program risks, PI Objectives, and dependency issues raised by teams. The primary purpose is to make adjustments to scope, resolve challenges, and provide guidance for Day 2 planning.
[References:, , SAFe 6.0 Website: PI Planning, , SPC 6.0 Guide: “Management meets to review progress, address challenges, and adjust scope as needed.”, , ===========, ]