During PI Planning, ROAMing risks (A) and assignment of business value to objectives (B) happen on Day 2. Day 1 is primarily focused on context-setting, team breakouts, and plan creation, while Day 2 includes management review, risk ROAMing, and business value assignment to PI Objectives.
“On Day 2 of PI Planning, teams assign business value to objectives and ROAM risks. Day 1 is for context and planning.”
(Source: SAFe 6.0 Framework: PI Planning; SPC 6.0 Guide “Launching an Agile Release Train”)
===========