Program Board (A): Visualizes Features, dependencies, and delivery milestones across teams.
Team PI Objectives (B): Clear, measurable commitments from each team.
Vote of confidence/commitment (D): ART-wide commitment to the PI plan.
“Top 10 Features,” “Portfolio Vision,” and “Iteration Goals” are not standard outputs of the PI Planning event.
“The key PI Planning outputs are the Program Board, Team PI Objectives, and a collective confidence vote/commitment.”
(Source: SAFe 6.0 Framework: PI Planning Outputs; SPC 6.0 Guide “Launching an Agile Release Train”)