At the end of day one of PI Planning, a management review and problem-solving meeting is held. During this meeting, management reviews the teams’ draft plans and makes any necessary changes to ensure alignment and address issues such as scope, resources, and dependencies before teams finalize their plans on day two.
[References:, , SAFe 6.0, “PI Planning” (Management Review and Problem-Solving), , SPC 6.0 Guide, “Launching an Agile Release Train”, , ]