According to the Apply Cadence, Synchronize with Cross-Domain Planning article on the Scaled Agile Framework website, cadence is the term that describes converting unpredictable events into predictable ones. The article states that “Cadence is the rhythm, or heartbeat, of the Agile Release Train (ART). It provides a steady and predictable pattern for planning, developing, and delivering value. Cadence helps teams manage the variability inherent in product development. By converting unpredictable events into predictable ones, cadence enables fast and reliable decision-making.” Therefore, the correct answer is C, cadence. The other options are not accurate, as they are not the terms that describe converting unpredictable events into predictable ones. Innovation and Planning (IP) Iteration (A) is a special iteration that occurs at the end of every Program Increment (PI) and provides an opportunity for innovation, planning, and system-level integration and testing. Program Increment (PI) Planning (B) is a face-to-face event that serves as the heartbeat of the ART, aligning all the teams on the ART to a shared mission and vision. Backlog refinement (D) is the process of breaking down, estimating, and prioritizing the backlog items.
Contribute your Thoughts:
Chosen Answer:
This is a voting comment (?). You can switch to a simple comment. It is better to Upvote an existing comment if you don't have anything to add.
Submit