The ART planning board is a key tool used during PI Planning in the Scaled Agile Framework (SAFe). It is utilized to visualize and communicate the critical aspects of the Program Increment (PI) planning process. According to the SAFe documentation, the ART planning board highlights the new feature delivery dates, feature dependencies among teams, and relevant milestones1. This visualization aids in the coordination and alignment of the teams within the Agile Release Train (ART).
The correct answer is B. Dependencies between teams, as the ART planning board specifically communicates the dependencies that exist between different teams working on the ART. This is crucial for ensuring that teams are aware of and can manage the interdependencies effectively, which is essential for the smooth delivery of value through the ART.