Question #: 37
Topic #: 4

The ART is near the end of the final Iteration of its first PI. Integration into staging is more challenging

than estimated. The ART adds a week to the Innovation and Planning (IP) Iteration for integration and

testing. Why is this action considered an anti-pattern?


A.

Overall, train velocity goes up, and the time-to-market goes down


B.

It decreases job satisfaction by removing autonomy and purpose


C.

It reduces the overall predictability established through cadence and synchronization


D.

It substantially decreases the predictability of the Solution Intent