The PO Sync is a regularly scheduled event for Product Owners (POs) and product management (PMs) with several important purposes. One of the primary purposes is to provide visibility into how well the Agile Release Train (ART) is progressing towards its Program Increment (PI) objectives. This involves assessing any scope changes to work and adjusting scope and priority as needed. The PO Sync enables the RTE, PMs, and POs to inspect and adapt the plan for the current PI, ensuring that the ART is on track to achieve its objectives and making necessary adjustments to the Program Backlog1.