During PI Planning, the Release Train Engineer (RTE) sees the team's excitement decline as Product

Management changes priorities, including the top ten Features in the ART Backlog. In addition,

Product Management is asking for new estimates, timelines, and scope changes. What is the likely

reason for this behavior?


A.

People are over-controlled and under-utilized


B.

Cadence and synchronization are not in alignment


C.

Management stakeholders are not involved in changing the system


D.

Lack of training and preparation for PI Planning