What are two benefits of having a well-executed Innovation and Planning (IP) Iteration? (Choose two.)


A.

Time for teams to plan, demo and improve together


B.

Occasional buffer time to deliver more predictably


C.

Higher flow of program-level business value


D.

Improved dependency management between teams


E.

Shorter lead times before Feature delivery