Scaled Agile SAFe Release Train Engineer (RTE) SAFe-RTE Question # 16 Topic 2 Discussion

Scaled Agile SAFe Release Train Engineer (RTE) SAFe-RTE Question # 16 Topic 2 Discussion

SAFe-RTE Exam Topic 2 Question 16 Discussion:
Question #: 16
Topic #: 2

At the end of day two of the Program Increment (PI) Planning event, the team's final plan review covers what information?


A.

Team Features, Stories, and team-level enablers


B.

Changes to capacity and load, final PI objectives, program risks and impediments


C.

Changes to iteration goals, measured velocity, and dependencies


D.

Planned Features, uncommitted objectives, and ROAMed risks