At the end of day two of the Program Increment (PI) Planning event, the team’s final plan review covers the Planned Features, uncommitted objectives, and ROAMed risks. This is a timeboxed session where teams present their final plans, PI Objectives, and risks and impediments12. The focus is on what the teams plan to deliver (Planned Features), the objectives that they aim to achieve but are not committed (uncommitted objectives), and the risks that have been identified and categorized according to the ROAM framework (Resolved, Owned, Accepted, Mitigated)2. This session is crucial as it provides a clear picture of the team’s direction and preparedness for the upcoming Program Increment. It also allows for transparency and alignment among all members of the Agile Release Train (ART).