Scaled Agile SAFe DevOps Practitioner Exam SDP (6.0) SAFe-DevOps Question # 23 Topic 3 Discussion

Scaled Agile SAFe DevOps Practitioner Exam SDP (6.0) SAFe-DevOps Question # 23 Topic 3 Discussion

SAFe-DevOps Exam Topic 3 Question 23 Discussion:
Question #: 23
Topic #: 3

What should the team be able to do after current-state mapping?


A.

Define a plan to reduce the lead time and increase Active Time


B.

Identify those responsible for the biggest bottlenecks in the process


C.

Describe the biggest bottlenecks in the delivery pipeline


D.

Define Enabler Features that will improve the Value Stream


Get Premium SAFe-DevOps Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.