ROAM is an acronym for Resolved, Owned, Accepted, Mitigated. ROAM is a technique for categorizing and managing PI risks during the final plan review in the PI planning event. PI risks are potential events or conditions that may have a negative impact on the PI objectives or outcomes. ROAM helps teams address their PI risks by assigning them to one of four states: Resolved (the risk has been eliminated or is no longer relevant); Owned (the risk has been assigned to a person or a team who is responsible for managing it); Accepted (the risk has been acknowledged and its impact has been factored into the plan); Mitigated (the risk has been reduced or its likelihood has been lowered). References: PI Planning, Final Plan Review