E_ACTAI_2403 Exam Topic 1 Question 9 Discussion:
Question #: 9
Topic #: 1

What is the result of fit-to-standard workshops?


A.

Detailed assessment of customer's current business processes


B.

Preparation of standard test cases and test scripts for end users


C.

Prioritization of the requirements backlog by the team


D.

Confirmation solution fit and identification of delta requirements