Activity recording (e.g., time or cost) for inspection lots of origin 01 (Goods Receipt) requires:
Inspection Operations with Work Centers (B): Operations in the inspection plan (transaction QP01) must have work centers assigned, as these link to activity types (e.g., labor) for recording effort or costs during inspection (SPRO > QM > Quality Planning > Inspection Planning).
Inspection Lot with a QM Order (D): A QM order (e.g., created via Customizing or lot assignment) is required to capture activity data (e.g., via transaction QE51N or CO11N), linking costs to the inspection lot (SPRO > QM > Quality Inspection > Inspection Lot Creation > Define Inspection Types).
Inspection Specifications with Master Inspection Characteristics (A): MICs define what’s inspected but aren’t prerequisites for activity recording.
Inspection Specifications with Inspection Methods (C): Methods guide execution, not activity recording setup.
Thus, "Inspection operations with work centers" and "Inspection lot with a QM order" are the correct answers.References: SAP Help Portal - "Activity Recording in QM"; SAP S/4HANA QM User Guide - "Cost Management".