In the context of a production order, Goods Receipt (A) and Order Settlement (D) are transactions that credit a production order. Goods Receipt credits the production order upon the receipt of the finished goods into inventory, reflecting the increase in stock. Order Settlement distributes the costs collected on the production order to the designated cost objects, such as cost centers or products, thereby crediting the order with the settled costs.References= SAP Production Planning (PP) and Controlling (CO) documentation.