In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish thematerial - by generating purchase requisitions for external procurement or planned orders for in-house production.References= SAP Material Management (MM) and Production Planning (PP) documentation.