Question #: 69
Topic #: 7

A customer needs to assign different public holiday calendars in their work schedule configuration. To which part of the HR structure is the public holiday calendar assigned?

Please choose the correct answer.

Response:


A.

Organizational structure


B.

Personnel structure


C.

Employee structure


D.

Enterprise structure