C_S4PPM_1909 Exam Topic 2 Question 14 Discussion:
Question #: 14
Topic #: 2

You are planning resources.

Which period types are available?

NOTE: There are 3 correct answers to this question.


A.

Weekly


B.

Hourly


C.

Monthly


D.

Daily


Get Premium C_S4PPM_1909 Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.