What do you use the check Conflict button for?
NOTE: There are 3 correct answers to this question
Adjustment of distribution of staffing
Adjustment of dates of roles
Adjustment of work according to roles assignment of a task
Adjustment of work according to resource availability
Adjustment of dates of staffing