An org has an existing process, built using Process Builder, on Opportunity that sets a custom field, CommissionBaseAmount__c, when
an Opportunity is edited and the Opportunity's Amount changes.
A developer recently deployed an Opportunity before update trigger that uses the CommissionBaseAmount__c and complex logic to calculate a
value for a custom field, CommissionAmount__c, when an Opportunity stage changes to Closed/Won.
Users report that when they change the Opportunity to Closed/Won and also change the Amount during the same save, the CommissionAmount__c is incorrect.
Which action should the developer take to correct this problem?