Certified-Business-Analyst Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

The delivery team at Cloud Kicks has Just conducted a successful sprint demo showcasing a new sales dashboard. However, the marketing team Is unhappy because the new lead automation they requested was missing from the deliverables and an Important new marketing campaign is starting the next day.

What did the business analyst fall to do during sprint planning'?


A.

Prioritize the sprint backlog with stakeholders


B.

Calculate the sprint capacity correctly


C.

Create a burndown list of sprint tasks