PRINCE2 Practitioner Exam Prince2-Practitioner Question # 59 Topic 6 Discussion

PRINCE2 Practitioner Exam Prince2-Practitioner Question # 59 Topic 6 Discussion

Prince2-Practitioner Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

Scenario:

The Ministry of Food Hygiene (MFH) has a quality management system which contains a document control process to manage all documentation requirements. The document control process was created by the MFH Quality Manager, who now maintains all of MFH's documents and performs an organization-wide configuration management role. The MFH Quality Manager will administer the configuration management procedure for the Restructuring project since this must comply with the MFH document control process.

What additional risk will this place on the project?


A.

None because risks associated with the centralization and rationalization of the Facilities Division will be managed by another project.


B.

These changes will delay stage 3 by three weeks.


C.

There is only £70k left in the project change budget.


D.

The reduced value of the contracted services required by the Outsourcing project may result in an insufficient number of proposals being received.