PRINCE2 7 Practitioner (7th Edition) Exam Prince2-Practitioner Question # 41 Topic 5 Discussion

PRINCE2 7 Practitioner (7th Edition) Exam Prince2-Practitioner Question # 41 Topic 5 Discussion

Prince2-Practitioner Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

The project has a cost tolerance of +5% I ·5%, of which stage 2 has a tolerance of +£45k 1-£45k.

Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Prince2-Practitioner Question 41