Question #: 39
Topic #: 4

Which statement is an appropriate entry for the project approach heading within the Project Brief?


A.

The initial estimates from the feasibility study will be verified during the initiation stage.


B.

MFH must better manage suppliers' performance.


C.

The Information Technology Division and the Facilities Division will be outsourced to a single service provider.


D.

The Project Manager will be responsible for ensuring that the agreed project approach remains an appropriate choice.