Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PRINCE2 7 Practitioner (7th Edition) Exam Prince2-Practitioner Question # 33 Topic 4 Discussion

PRINCE2 7 Practitioner (7th Edition) Exam Prince2-Practitioner Question # 33 Topic 4 Discussion

Prince2-Practitioner Exam Topic 4 Question 33 Discussion:
Question #: 33
Topic #: 4

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?


A.

Review the stage status


B.

Review work package status


C.

Report Highlights


D.

Take corrective action


Get Premium Prince2-Practitioner Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.