Question #: 28
Topic #: 3

CLOSING A PROJECT

The Health and Safety Training Project is part of a strategic program for ABC. The updated benefits management approach needs to be checked when the products are being handed over. This check should ensure that it includes appropriate activities to assess whether the actual course sales meet the agreed forecast in the business case.

Which role should undertake this review as part of the 'closing a project' process?


A.

Program management.


B.

Project board.


C.

Project manager.


D.

Project assurance.